By the MyToolers team at 182 AdFlow (Dubai & Lahore) · Last updated:
Why one day can matter
When someone resigns, takes annual leave or is given a deadline, everyone agrees on the number of days: 30 days' notice, 14 days' leave, 5 working days to reply. They often don't agree on the dates. Is the day the letter was handed over day one? Do Saturdays count? Does "one month" mean 30 days?
A single day can change the last working day, the final salary, whether leave is fully used, and in the UAE even whether an employee has reached one year of service for gratuity. This guide shows a simple way to count, with worked examples you can check yourself.
Step 1: Read what the contract and law actually say
Start with the employment contract or appointment letter, then the company handbook. Look for three things: how long the notice or leave is, whether it is counted in calendar days or working days, and how notice must be given (by email, a signed letter, or through an HR system).
In the UAE private sector, Federal Decree-Law No. 33 of 2021 sets the notice period at no less than 30 days and no more than 90 days, and gives employees at least 30 days of annual leave a year once they have completed a year of service. In Pakistan, notice and leave terms usually come from the appointment letter, company policy and the labour laws that apply to the business, which differ by province and type of employer.
Laws and executive rules can change, so confirm the current position with MOHRE in the UAE or the relevant provincial labour department in Pakistan before relying on a figure in a dispute.
Step 2: Agree which date is day one
This is where most disagreements start. Some employers treat the day the notice is received as day one; others start counting the next day. Neither is wrong if the contract says so, but both sides should know which method is used, and it is best to confirm it in writing when the notice is accepted.
Worked example: an employee hands in a resignation with 30 days' notice on Tuesday 10 March 2026.
If 10 March is day one, the 30th day is Wednesday 8 April 2026.
If counting starts the next day, 11 March is day one and the 30th day is Thursday 9 April 2026.
To check it, count from the start date to the end date with the end date included: 11 March to 9 April gives 21 days in March (11 to 31) plus 9 days in April, which is 30.
Step 3: Calendar days or working days?
Notice periods are usually counted in calendar days, so weekends and public holidays fall inside the period. Leave and reply deadlines are often counted in working days, which is where weekends and holidays come out.
Worked example: leave from Monday 6 April to Friday 17 April 2026, both days included. That is 12 calendar days. With a Monday-to-Friday week, there are 10 working days, because two weekend days (Saturday 11 and Sunday 12 April) fall in between. If the business works Monday to Saturday, as many shops and workshops in Pakistan do, the same dates contain 11 working days, because only Sunday is off.
Then remove any official public holidays that fall in the period. Holidays differ by country and Islamic holidays move each year with the moon sighting, so check the announced dates for that year rather than last year's list.
Whether annual leave is counted in calendar or working days changes how long a holiday lasts, so look for the exact wording in your contract and ask HR if it is not clear.
Step 4: "One month" is not always 30 days
A notice period written as "one month" or "three months" follows the calendar, so its length in days depends on which months it covers. A period written as "30 days" or "90 days" is a fixed count.
Worked example: notice starts on 1 February 2026. Three calendar months, ending the day before the same date three months later, runs to 30 April 2026, which is 89 days (28 in February, 31 in March and 30 in April). A 90-day period starting on the same date ends on 1 May 2026. If the contract says "three months" but HR counts 90 days, the two dates will be one day apart.
Step 5: Work out part-month pay and check gratuity
When the last working day falls in the middle of a month, the final salary is usually paid for the days worked. Contracts and payroll systems use different daily rates: some divide the monthly salary by 30, some by the number of days in that month, and some by working days.
Worked example: salary AED 6,000 a month, last working day Monday 9 February 2026, so 9 days are paid. Dividing by 30: 6,000 ÷ 30 = AED 200 a day, and 9 × 200 = AED 1,800. Dividing by the 28 days of February: 6,000 ÷ 28 = AED 214.29 a day, and 9 × 214.29 = about AED 1,928.57. Same salary, same dates, and the result differs by about AED 129, so check which method your contract or payroll uses.
In the UAE, the last working day also decides how much service counts for gratuity, which needs at least one full year. Someone who joined on 1 April 2025 and resigns on 10 March 2026 with 30 days' notice, counted from the next day, finishes on 9 April 2026. That is 374 days of service counting both the first and last day, just over one year. If they agreed to leave on 10 March instead, service would be 344 days and no gratuity would be due. Check the last working day your employer records before agreeing to shorten the notice.
Common mistakes
Not agreeing whether the day notice is given counts as day one.
Counting a period in working days when the contract says calendar days, or the other way round.
Treating "one month" and "30 days" as the same thing.
Forgetting public holidays when counting working days, or using last year's holiday dates.
Not keeping proof of when notice was given, such as an email, a signed copy or an HR system record.
Taking leave during the notice period without first agreeing in writing whether those days still count towards the notice.
How MyToolers helps
The free MyToolers Days Between Dates calculator counts the total days between two dates, with an option to include the end date, and shows weeks, weekdays (Monday to Friday), weekend days and approximate months. It does not remove public holidays, so subtract any that apply to you, and if your business works six days a week, add back the Saturdays shown in the weekend count.
For UAE end-of-service pay, the free UAE Gratuity Calculator takes your last basic salary, joining date, last working day and any unpaid leave days, and estimates the gratuity under the current labour law, including whether the one-year minimum has been met. Both tools give planning estimates; for a dispute, confirm the figures with your employer, MOHRE or the relevant labour authority.